STATUS REPORT OF PURVA FOUNTAINSQUARE AS ON 31.03.2008
(Blocks: A, B, C, D, E, F, G, H, J, K, L, M, N, P Q, R & Podium)

  • Basement Excavation: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P Q, and R Completed. And PODIUM Completed.
  • Excavation for Footing: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R- Completed, and Podium Completed.
  • Plain Cement Concrete Including Stilt: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R - Completed, Podium - Completed.
  • Column footing including stilt: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R - Completed, Podium - Completed.
  • Column / Lift wall - Basement floor: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R - Completed, Podium - Completed.
  • Retaining wall - Basement Floor: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, Block R - Completed, Podium - Completed.
  • Retaining Wall -Water proofing: Block A, B, C, D, E, F, G, H, J, K, L, M, N, Q, Block R -Completed, Podium-Completed.
  • Ground Floor Slab except stilt portion: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, & R - Completed. Podium - Completed.
  • Ground Floor Column: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R, Completed, Podium - 100% Completed.
  • First Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R - Completed, Podium - 85% Completed.
  • First Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R, Completed, Podium - 75% Completed.
  • Second Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
  • Second Floor Column: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
  • Third Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
  • Third Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q , R Completed.
  • Fourth Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q , R Completed.
  • Fourth Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
  • Fifth Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
  • Fifth Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
  • Sixth Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R Completed.
  • Sixth Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q Completed.
  • Seventh Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q Completed.
  • Seventh Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q Completed.
  • Eight Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q - Completed.
  • Eight Floor Columns: Block A, B, C, D,E,F, G, H,J, K, L, M, N, P & Q Completed.
  • Ninth Floor Slab: Block A, B, C, E, F, G, H,J, K, L, M, N, P&Q - Completed.
  • Ninth Floor Columns: Block A, B, C, E, F, H, J, K, L, M, N, P& Q - Completed.
  • Tenth Floor Slab: Block A, B, C, E,F,G, H, J,K, L, M, N, P&Q - Completed.
  • Tenth Floor Columns: Block A, B, C, E,F, G, H,J, K, L, M, N, P&Q - Completed.
  • Eleventh Floor Slab: Block A, B, C, E,F, G, H,J,K, L, M, N,P & Q - Completed.
  • Eleventh Floor Columns: Block A, B, C, E,F ,G, H,J, K, L, M, N,P & Q - Completed.
  • Twelfth Floor Slab: Block A, B, C, D, E,F, G, H,J, K, L, M, N ,P & Q - Completed.
  • Twelfth Floor Columns: Block A, B, C, E, F,G, H, J,K, L,M ,N,P& Q- Completed.
  • Thirteenth Floor Slab: Block A, B, C,D,E,F, G, H,J, K, L, M, N,P& Q - Completed.
  • Thirteenth Floor Columns: Block A, B, C,D ,E,F,G, H, J,K, L, M, N,P & Q - Completed.
  • Roof Slab: Block A,B,C,D,E, F,G,H,J,K, L,M,N , P,Q & R - 100% Completed.
  • Roof stop structures: Block A,B,C,D,E, F,G,H,J,K, L,M,N, P,Q & R 100% completed.
  • Jelly & Storm Water Drain: Block A,B,C,D, E,F,G,H, J,K,L,M,N,P,Q -100% Completed.
  • PCC below Floor: Block A,B,C,D,E, F,G,H,J,K,L,M,N,P,Q -100% Completed.
  • Grade Slab: Block A,B,C,D,E,F,G,H,J, K,L, M,N,P&Q -100% Completed.
  • Basement Floor Ceiling plaster: Block B, C,D, E, F, G, H, J, L, M, N, P & R Completed, Block K - 95% Completed, Block Q - 95% completed.
  • Ground Floor Ceiling Plaster - Block B, C, D, E, F, G, H, J, K, L,M, N,P ,Q & R - 100% Completed.
  • 1st Floor Ceiling Plaster: Block A, B, C ,D,E,F, G, H,J,K, L, M, N, P,Q & R- Completed.
  • Second Floor Ceiling Plaster: Block A, B, C,D, E, F, G, H, J, K, L,M, N, P, Q,R - Completed.
  • Third Floor Ceiling Plaster: Block A, B, C,D,E, F, G, H,J,K, L,M, N, P, Q & R - Completed.
  • Fourth Floor Ceiling Plaster: Block A,B, C,D,E, F, G, H,J, K, L,M N,P, Q, R- Completed.
  • Fifth Floor Ceiling Plaster: Block A, B,C,D, E, F, G, H, J,K, L,M, N,P, Q & R -Completed.
  • Sixth Floor Ceiling Plaster: Block A,B,C,D, E, F,G, H, J,K, L,M,N,P & Q - Completed.
  • Seventh Floor Ceiling Plaster: Block: A,B,C,D,E, F, G, H,J, K, L,M,N,P&Q -Completed.
  • Eight Floor Ceiling Plaster: Block A,B,C ,D,E, F,G, H,J,K, L, M, N, P &Q - 100% Completed.
  • Ninth Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H,J,K, L,M,N,P,&Q-100% Completed.
  • Tenth Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H, J,K,L, M ,N,P,Q - 100% Completed.
  • Eleventh Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q - 100% Completed.
  • Twelfth Floor Ceiling Plaster: Block A,B,C,D,E,F, G,H,J, K,L,MN,P,Q - 100% Completed.
  • Thirteenth Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q -100% Completed.
  • Terrace floor masonry - Block -A,B,C,D,J,K,L,M,N,P,R - 100% Completed, Block E,F,G,H - 90% completed, Block Q- 95% completed.
  • Roof Top Structure: Block A,B,C,D,E,F,G,H,J,L,N,P,Q,R - 100% Completed, Block K - 80% Completed, Block M - 70% Completed.
  • 1st Floor Masonry: Block A, B,C,D, E,F, G, H, J, K, L, M, N,P,Q & R - Completed.
  • Second Floor Masonry: Block A, B,C,D, E,F,G,H, J, K, L, M, N, P, Q & R - Completed.
  • Third Floor Masonry: Block A, B,C,D,E,F,G,H,J,K,L,M,N,P,Q& R - 100% Completed.
  • Fourth Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q & R-100% Completed.
  • Fifth Floor Masonry: Block A, B,C,D, E,F,G,H, J,K, L, M,N,P,Q &R - 100% Completed.
  • Sixth Floor Masonry: Block A ,B,C,D,E,F,G,H, J, K, L, M,N, P &Q- 100% Completed.
  • Seventh Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M, N,P&Q- 100% Completed.
  • Eight Floor Masonry: Block A,B,C,D,E,F,G,H,J,K, L,M,N,P & Q - 100% Completed.
  • Ninth Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Tenth Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q -100% Completed.
  • Eleventh Floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q - 100% Completed.
  • Twelfth Floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q - 100% Completed.
  • Thirteenth Floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q -100% Completed.
  • Terrace Floor Masonry: BlockA,B,C,D,H,J,K,L,M,N, P&R - 100% Completed, Block E,F,G - 90% Completed, Block 95% completed.
  • First Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,L,M,N,K,P,Q&R-100% Completed.
  • Second Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R - 100% Completed.
  • Third Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R- 100% Completed.
  • Fourth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R- 100% Completed.
  • Fifth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R- 100% Completed.
  • Sixth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Seventh Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Eight Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Ninth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Tenth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Eleventh Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Twelfth floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
  • Thirteenth Floor: Block A,B,C,N - 95% Completed, Block D,E,F,G,H,K,L,P,Q -100% Completed, Block M - 80% Completed.
  • Terrace Internal Plastering: Block A,B,C, G,J,N - 95% Completed, Block D,E,F,H,L,M,R -100% Completed, Block K,P,Q - 90% Completed.
  • Door Frame Fixing: Block A,B,C,D,E,G,H,J,K,L,M,N,P,R-100% Completed, Block F&Q -95% Completed .
  • Grill Fixing: Block A,B,C,D,F,G,H,L,M,N,P,R - 100% Completed, Block D,F - 95% Completed, Block J - 90% Completed, Block K & Q - 75% Completed.
  • Water Proofing - Balconies& Sunken Slabs: Block A,B,C,D,E,F,G,H,L,M,N,R-100% Completed, Block J,K,P,Q - 90% Completed.
  • Terrace floor tiling - Block N - 100% completed, Block A &C -20% completed,
  • Block H & M - 25% completed, Block L - 90% completed.
  • External Plastering: Block A,B,C ,L,N,R- 100% Completed, Block D,E, F - 99% Completed, Block G,H,M - 95% Completed, Block J,K,P -80% Completed, Block Q - 65% Completed.
  • Internal Electrical Works - Conducting: Block A,B,C,D,E,F,G,H,L,M,N,R - 100% Completed, Block J,Q - 90% Completed, Block K,P - 95% Completed.
  • Internal Plumbing Works: Block A,B,C,E,G,H,J,L,M,N - 95% Completed, Block D,F,K - 90% Completed, Block Q - 80% Completed, Block P - 75% Completed.
  • External Eletrical Works - HT & DG Works: Block E - 90% Completed.
  • External Sewer Lines - 100% completed.
  • Staircase & Handrail Fixing & Finishing: Block A,B,C,D,E,F,G,H,J,K,L,M,N,Q,R - 100% Completed, Block P - 95% Completed.
  • Kitchen Platforms & Dado: Block A,B,C - 99% Completed, Block D,E,F - 85% Completed, Block G,L,M,R,N - 100% Completed, Block H - 95% Completed, Block J - 70% Completed, Block P - 60% completed, Block K - 80% Completed, Block Q - 50% Completed.
  • Flooring & Dadoing: Block A,B,C - 99% Completed, Block D,E - 90% Completed, Block F,G,H,R - 95% Completed, Block J& K - 80% Completed, Block L,M,N -100% Completed, Block P&Q - 70% completed.
  • Door Shutter & al Window fixing: Block A,B,C - 99% Completed, Block D - 60% Completed, Block E,F,G - 70% Completed Block H,J - 80% Completed, Block K,P,Q - 60% Completed, Block L - 95% Completed, Block M,N - 90% Completed, Block R - 100% Completed.
  • Internal Painting: Block A,G,L,R- 90% Completed, Block B,C - 85% Completed, Block D - 25% Completed, Block E ,H- 50% Completed, Block F- 55% Completed, Block J,K - 40% Completed, Block M - 80% Completed, Block M -75% Completed, Block N - 95% Completed, Block Q 60% completed.
  • Lobby Finishing: Block A,B,C,D,H- 85% Completed, Block E,G,J,K - 80% Completed, Block F - 50% Completed, Block L -95% Completed, Block N,P,Q - 70% completed, Block K ,P - 50% completed.
  • Lift Supply & Installation: Block A,B,C,H,L,M,N - 100% Completed, Block R&G - 95% Completed, Block D,E - 90% Completed, Block F - 85% completed, Block J,N - 40% completed, Block K - 60% completed, Block Q - 30% completed.
  • Fire Fighting Works: 90% Completed.
  • Compound wall: 95% Completed.
STP
  • Excavation: 100% Completed
  • Raft base/walls/Top slab: 100%/100%/100% Completed.
Club House
  • Structure: 100% Completed.
  • Finishing: 25% Completed.