STATUS REPORT OF PURVA FOUNTAINSQUARE AS ON 31.03.2008
(Blocks: A, B, C, D, E, F, G, H, J, K, L, M, N, P Q, R & Podium)
- Basement Excavation: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P Q, and R Completed. And PODIUM Completed.
- Excavation for Footing: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R- Completed, and Podium Completed.
- Plain Cement Concrete Including Stilt: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R - Completed, Podium - Completed.
- Column footing including stilt: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R - Completed, Podium - Completed.
- Column / Lift wall - Basement floor: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R - Completed, Podium - Completed.
- Retaining wall - Basement Floor: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, Block R - Completed, Podium - Completed.
- Retaining Wall -Water proofing: Block A, B, C, D, E, F, G, H, J, K, L, M, N, Q, Block R -Completed, Podium-Completed.
- Ground Floor Slab except stilt portion: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, & R - Completed. Podium - Completed.
- Ground Floor Column: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R, Completed, Podium - 100% Completed.
- First Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R - Completed, Podium - 85% Completed.
- First Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R, Completed, Podium - 75% Completed.
- Second Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
- Second Floor Column: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
- Third Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
- Third Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q , R Completed.
- Fourth Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q , R Completed.
- Fourth Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
- Fifth Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
- Fifth Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q, R Completed.
- Sixth Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P, Q & R Completed.
- Sixth Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q Completed.
- Seventh Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q Completed.
- Seventh Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q Completed.
- Eight Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N, P & Q - Completed.
- Eight Floor Columns: Block A, B, C, D,E,F, G, H,J, K, L, M, N, P & Q Completed.
- Ninth Floor Slab: Block A, B, C, E, F, G, H,J, K, L, M, N, P&Q - Completed.
- Ninth Floor Columns: Block A, B, C, E, F, H, J, K, L, M, N, P& Q - Completed.
- Tenth Floor Slab: Block A, B, C, E,F,G, H, J,K, L, M, N, P&Q - Completed.
- Tenth Floor Columns: Block A, B, C, E,F, G, H,J, K, L, M, N, P&Q - Completed.
- Eleventh Floor Slab: Block A, B, C, E,F, G, H,J,K, L, M, N,P & Q - Completed.
- Eleventh Floor Columns: Block A, B, C, E,F ,G, H,J, K, L, M, N,P & Q - Completed.
- Twelfth Floor Slab: Block A, B, C, D, E,F, G, H,J, K, L, M, N ,P & Q - Completed.
- Twelfth Floor Columns: Block A, B, C, E, F,G, H, J,K, L,M ,N,P& Q- Completed.
- Thirteenth Floor Slab: Block A, B, C,D,E,F, G, H,J, K, L, M, N,P& Q - Completed.
- Thirteenth Floor Columns: Block A, B, C,D ,E,F,G, H, J,K, L, M, N,P & Q - Completed.
- Roof Slab: Block A,B,C,D,E, F,G,H,J,K, L,M,N , P,Q & R - 100% Completed.
- Roof stop structures: Block A,B,C,D,E, F,G,H,J,K, L,M,N, P,Q & R 100% completed.
- Jelly & Storm Water Drain: Block A,B,C,D, E,F,G,H, J,K,L,M,N,P,Q -100% Completed.
- PCC below Floor: Block A,B,C,D,E, F,G,H,J,K,L,M,N,P,Q -100% Completed.
- Grade Slab: Block A,B,C,D,E,F,G,H,J, K,L, M,N,P&Q -100% Completed.
- Basement Floor Ceiling plaster: Block B, C,D, E, F, G, H, J, L, M, N, P & R Completed, Block K - 95% Completed, Block Q - 95% completed.
- Ground Floor Ceiling Plaster - Block B, C, D, E, F, G, H, J, K, L,M, N,P ,Q & R - 100% Completed.
- 1st Floor Ceiling Plaster: Block A, B, C ,D,E,F, G, H,J,K, L, M, N, P,Q & R- Completed.
- Second Floor Ceiling Plaster: Block A, B, C,D, E, F, G, H, J, K, L,M, N, P, Q,R - Completed.
- Third Floor Ceiling Plaster: Block A, B, C,D,E, F, G, H,J,K, L,M, N, P, Q & R - Completed.
- Fourth Floor Ceiling Plaster: Block A,B, C,D,E, F, G, H,J, K, L,M N,P, Q, R- Completed.
- Fifth Floor Ceiling Plaster: Block A, B,C,D, E, F, G, H, J,K, L,M, N,P, Q & R -Completed.
- Sixth Floor Ceiling Plaster: Block A,B,C,D, E, F,G, H, J,K, L,M,N,P & Q - Completed.
- Seventh Floor Ceiling Plaster: Block: A,B,C,D,E, F, G, H,J, K, L,M,N,P&Q -Completed.
- Eight Floor Ceiling Plaster: Block A,B,C ,D,E, F,G, H,J,K, L, M, N, P &Q - 100% Completed.
- Ninth Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H,J,K, L,M,N,P,&Q-100% Completed.
- Tenth Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H, J,K,L, M ,N,P,Q - 100% Completed.
- Eleventh Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q - 100% Completed.
- Twelfth Floor Ceiling Plaster: Block A,B,C,D,E,F, G,H,J, K,L,MN,P,Q - 100% Completed.
- Thirteenth Floor Ceiling Plaster: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q -100% Completed.
- Terrace floor masonry - Block -A,B,C,D,J,K,L,M,N,P,R - 100% Completed, Block E,F,G,H - 90% completed, Block Q- 95% completed.
- Roof Top Structure: Block A,B,C,D,E,F,G,H,J,L,N,P,Q,R - 100% Completed, Block K - 80% Completed, Block M - 70% Completed.
- 1st Floor Masonry: Block A, B,C,D, E,F, G, H, J, K, L, M, N,P,Q & R - Completed.
- Second Floor Masonry: Block A, B,C,D, E,F,G,H, J, K, L, M, N, P, Q & R - Completed.
- Third Floor Masonry: Block A, B,C,D,E,F,G,H,J,K,L,M,N,P,Q& R - 100% Completed.
- Fourth Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q & R-100% Completed.
- Fifth Floor Masonry: Block A, B,C,D, E,F,G,H, J,K, L, M,N,P,Q &R - 100% Completed.
- Sixth Floor Masonry: Block A ,B,C,D,E,F,G,H, J, K, L, M,N, P &Q- 100% Completed.
- Seventh Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M, N,P&Q- 100% Completed.
- Eight Floor Masonry: Block A,B,C,D,E,F,G,H,J,K, L,M,N,P & Q - 100% Completed.
- Ninth Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Tenth Floor Masonry: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q -100% Completed.
- Eleventh Floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q - 100% Completed.
- Twelfth Floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q - 100% Completed.
- Thirteenth Floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q -100% Completed.
- Terrace Floor Masonry: BlockA,B,C,D,H,J,K,L,M,N, P&R - 100% Completed, Block E,F,G - 90% Completed, Block 95% completed.
- First Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,L,M,N,K,P,Q&R-100% Completed.
- Second Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R - 100% Completed.
- Third Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R- 100% Completed.
- Fourth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R- 100% Completed.
- Fifth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q,R- 100% Completed.
- Sixth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Seventh Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Eight Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Ninth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Tenth Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Eleventh Floor Internal Plastering: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Twelfth floor: Block A,B,C,D,E,F,G,H,J,K,L,M,N,P,Q- 100% Completed.
- Thirteenth Floor: Block A,B,C,N - 95% Completed, Block D,E,F,G,H,K,L,P,Q -100% Completed, Block M - 80% Completed.
- Terrace Internal Plastering: Block A,B,C, G,J,N - 95% Completed, Block D,E,F,H,L,M,R -100% Completed, Block K,P,Q - 90% Completed.
- Door Frame Fixing: Block A,B,C,D,E,G,H,J,K,L,M,N,P,R-100% Completed, Block F&Q -95% Completed .
- Grill Fixing: Block A,B,C,D,F,G,H,L,M,N,P,R - 100% Completed, Block D,F - 95% Completed, Block J - 90% Completed, Block K & Q - 75% Completed.
- Water Proofing - Balconies& Sunken Slabs: Block A,B,C,D,E,F,G,H,L,M,N,R-100% Completed, Block J,K,P,Q - 90% Completed.
- Terrace floor tiling - Block N - 100% completed, Block A &C -20% completed,
- Block H & M - 25% completed, Block L - 90% completed.
- External Plastering: Block A,B,C ,L,N,R- 100% Completed, Block D,E, F - 99% Completed, Block G,H,M - 95% Completed, Block J,K,P -80% Completed, Block Q - 65% Completed.
- Internal Electrical Works - Conducting: Block A,B,C,D,E,F,G,H,L,M,N,R - 100% Completed, Block J,Q - 90% Completed, Block K,P - 95% Completed.
- Internal Plumbing Works: Block A,B,C,E,G,H,J,L,M,N - 95% Completed, Block D,F,K - 90% Completed, Block Q - 80% Completed, Block P - 75% Completed.
- External Eletrical Works - HT & DG Works: Block E - 90% Completed.
- External Sewer Lines - 100% completed.
- Staircase & Handrail Fixing & Finishing: Block A,B,C,D,E,F,G,H,J,K,L,M,N,Q,R - 100% Completed, Block P - 95% Completed.
- Kitchen Platforms & Dado: Block A,B,C - 99% Completed, Block D,E,F - 85% Completed, Block G,L,M,R,N - 100% Completed, Block H - 95% Completed, Block J - 70% Completed, Block P - 60% completed, Block K - 80% Completed, Block Q - 50% Completed.
- Flooring & Dadoing: Block A,B,C - 99% Completed, Block D,E - 90% Completed, Block F,G,H,R - 95% Completed, Block J& K - 80% Completed, Block L,M,N -100% Completed, Block P&Q - 70% completed.
- Door Shutter & al Window fixing: Block A,B,C - 99% Completed, Block D - 60% Completed, Block E,F,G - 70% Completed Block H,J - 80% Completed, Block K,P,Q - 60% Completed, Block L - 95% Completed, Block M,N - 90% Completed, Block R - 100% Completed.
- Internal Painting: Block A,G,L,R- 90% Completed, Block B,C - 85% Completed, Block D - 25% Completed, Block E ,H- 50% Completed, Block F- 55% Completed, Block J,K - 40% Completed, Block M - 80% Completed, Block M -75% Completed, Block N - 95% Completed, Block Q 60% completed.
- Lobby Finishing: Block A,B,C,D,H- 85% Completed, Block E,G,J,K - 80% Completed, Block F - 50% Completed, Block L -95% Completed, Block N,P,Q - 70% completed, Block K ,P - 50% completed.
- Lift Supply & Installation: Block A,B,C,H,L,M,N - 100% Completed, Block R&G - 95% Completed, Block D,E - 90% Completed, Block F - 85% completed, Block J,N - 40% completed, Block K - 60% completed, Block Q - 30% completed.
- Fire Fighting Works: 90% Completed.
- Compound wall: 95% Completed.
STP
- Excavation: 100% Completed
- Raft base/walls/Top slab: 100%/100%/100% Completed.
Club House
- Structure: 100% Completed.
- Finishing: 25% Completed.
|