BLOCK - A / WING 1
- M20 grade concrete of 50mm thick (Screed) – 100% completed.
- PCC M20 grade, concrete toilet S.H.R, L.M.R – 100% completed.
- M25 grade concrete in Beam & Ducts – 100% completed.
- M15 concrete for Chajja & Sills – 100% completed.
- 100,150,200mm thick Block Masonry – 100% completed.
- Kota stone Flooring in staircase – 100% completed.
- Kota Stone Skirting in staircase - 100% completed.
- Ceiling & Wall painting internal O.B.D – 44.22% completed.
- Toilet Dadooing – 95.16% completed.
- Toilet Flooring – 93.44% completed.
- Wooden Flooring – 3.00% completed.
- Living Vitrified Tiles area over Marble flooring – 9.30% completed.
- Steel reinforcement for Beams – 100% completed.
- Balcony staircase hand railing – 100% completed.
- P.O.P Cornice – 98% completed.
- Vault roof of Terrace (Structural Steel) – 42.80% completed.
- Doors Shutters & fittings – 100% completed.
- Door Shutter Polishing – 2.50% completed.
- Acid wash in toilets – 2.89% completed.
- C.P. Fitting in Toilets – 2.89% completed.
- Compound wall work East wall side – 18.92% completed.
- Ramp connecting wing – 2 – 70.40% completed.
- Marble Flooring for living & Dining – 99% completed.
- Flooring in Bedroom – 97% completed.
- Marble Flooring in corridor – 60% completed.
1. Block A Wing II
- Excavation in all kinds of soil for foundation – 100% completed.
- Excavation of soft or disintegrated rock – 100% completed.
- P.C.C 1:4:8 in foundation, column, footing & below flooring – 100% completed.
- Concrete M20 for R.W – 100% completed.
- M20 concrete in footing & pedestal & Slab – 100% completed.
- M30 concrete for column in Lower & Upper Basement – 100% completed.
- M20 concrete for slab & beam – 100% completed.
- Concrete for lintel (M20) – 100% completed.
- M25 concrete sump tank, storm water tank, O.H.T – 100% completed.
- M30 concrete for shear wall – 100% completed.
- Masonry works 200/100mm thick – 100% completed.
- Masonry works 150mm thick – 100% completed.
- IPS Flooring for L.B & U.B – 50% completed.
- 20mm thick granite counter slabs for kitchen – 96% completed.
- Kota stone for stair case – 100% completed.
- Marble flooring 20mm thick in flat – 96% completed.
- Vitrified tile flooring in Bedrooms – 100% completed.
- Ceramic tile flooring & dadoing in toilet – 100% completed.
- PVC Beading above skirting & Dadoo – 100% completed.
- Steel Reinforcement for slabs & Beams – 100% completed.
- M.S. Railing for stair case – 100% completed.
- Plastering Internal – 100% completed.
- External Plastering – 100% completed.
- Water proofing plaster20mm thick for O.H.T – 100% completed.
- Water proofing in terrace, retaining wall & toilets – 100% completed.
- Painting O.B.D – 100% completed.
- A.T.T – 100% completed.
- Wooden Flooring – 90.40% completed.
- C.P. Fitting in flats – 88% completed.
- Lift Work – 30% completed.
- External painting including hand railing – 30% completed.
- False Ceiling in toilets & Kitchen – 60% completed.
- Insulation of sanitary pipes – 98.21% completed.
- Lobby Flooring – 50% completed.
- Doors & Fittings - 93.50% completed.
- Door Polishing - 64.77% completed.
- Fenesta Doors & Windows – 87.21% completed.
Block A Wing III
- Excavation in all kinds of soil for foundation – 100% completed.
- Laying P.C.C - 100% completed
- M25 Grade for Raft – Slab & Lift – Pit - 100% completed
- M20 grade for Retaining Wall - 42% completed
- M45 for column junctions Lower – Basement & Upper Basement - 75% completed
- Steel – Reinforcement for foundation (Raft) - 100% completed
- Steel – Reinforcement for Upper Basement floor - 100% completed
- Shuttering for columns & G.F. Roofslab – 60% completed
STP
- Earthwork Exacavation - 100% completed
- P.C.C - 81% completed
- Concreting – 34.27% completed.
- Shuttering – 42% completed
- Reinforcement – 51% completed.
BLOCK – A / WING – I&II
- Over all Conduiting – 92% completed.
- Switch Box Fixing – 98% completed.
- Circuitry Wiring – 88.88% completed.
- Point Wiring – 85.88% completed.
- Switch plate Fixing - 13.33% completed.
- Testing 4.65% completed.
- Head over of flats – 2.32% completed.
Electrical Internal work Progress Wing – II
- Over all Conduiting – 80.86% completed.
- Switch Box Fixing – 95.83% completed.
- Circuitry Wiring – 97.32% completed.
- Point Wiring – 92.75% completed.
- Switch plate Fixing - 98.55% completed.
- Testing - 23.80% completed.
Electrical External work Progress Wing – I & II
- Lift room & Shaft Electrical Works – 50% completed.
- Electrical duct conduit works – 20% completed.
- Cable Tray & Cable Works - 5% completed.
|
|
|
| Project Summary |
Project Type:
Residential Apartments
Location:
Sanjaynagar, Bangalore.
Distances:
7 kms from M.G. Road
11 kms from Airport
Unit Types:
2 & 3 Bedroom Apts.
Unit Cost:
Rs. 80 Lakhs onwards.
US$ 177,700 onwards.
Project Status:
Under Construction
|
|
 |
| |
 |
Purva Privileges
A first of its kind Program in the Indian Real Estate Industry.
Refer and get rewarded
With Purva Privileges you can refer a friend or a relative to us and get rewarded.
» Learn More |
 |
|