Status report of Purva Atria as on 31.05.08
Photographs as on 26.05.08
» See Progress Photographs

BLOCK - A / WING 1
  • M20 grade concrete of 50mm thick (Screed) – 100% completed.
  • PCC M20 grade, concrete toilet S.H.R, L.M.R – 100% completed.
  • M25 grade concrete in Beam & Ducts – 100% completed.
  • M15 concrete for Chajja & Sills – 100% completed.
  • 100,150,200mm thick Block Masonry – 100% completed.
  • Kota stone Flooring in staircase – 100% completed.
  • Kota Stone Skirting in staircase - 100% completed.
  • Ceiling & Wall painting internal O.B.D – 44.22% completed.
  • Toilet Dadooing – 95.16% completed.
  • Toilet Flooring – 93.44% completed.
  • Wooden Flooring – 3.00% completed.
  • Living Vitrified Tiles area over Marble flooring – 9.30% completed.
  • Steel reinforcement for Beams – 100% completed.
  • Balcony staircase hand railing – 100% completed.
  • P.O.P Cornice – 98% completed.
  • Vault roof of Terrace (Structural Steel) – 42.80% completed.
  • Doors Shutters & fittings – 100% completed.
  • Door Shutter Polishing – 2.50% completed.
  • Acid wash in toilets – 2.89% completed.
  • C.P. Fitting in Toilets – 2.89% completed.
  • Compound wall work East wall side – 18.92% completed.
  • Ramp connecting wing – 2 – 70.40% completed.
  • Marble Flooring for living & Dining – 99% completed.
  • Flooring in Bedroom – 97% completed.
  • Marble Flooring in corridor – 60% completed.
1. Block A Wing II
  • Excavation in all kinds of soil for foundation – 100% completed.
  • Excavation of soft or disintegrated rock – 100% completed.
  • P.C.C 1:4:8 in foundation, column, footing & below flooring – 100% completed.
  • Concrete M20 for R.W – 100% completed.
  • M20 concrete in footing & pedestal & Slab – 100% completed.
  • M30 concrete for column in Lower & Upper Basement – 100% completed.
  • M20 concrete for slab & beam – 100% completed.
  • Concrete for lintel (M20) – 100% completed.
  • M25 concrete sump tank, storm water tank, O.H.T – 100% completed.
  • M30 concrete for shear wall – 100% completed.
  • Masonry works 200/100mm thick – 100% completed.
  • Masonry works 150mm thick – 100% completed.
  • IPS Flooring for L.B & U.B – 50% completed.
  • 20mm thick granite counter slabs for kitchen – 96% completed.
  • Kota stone for stair case – 100% completed.
  • Marble flooring 20mm thick in flat – 96% completed.
  • Vitrified tile flooring in Bedrooms – 100% completed.
  • Ceramic tile flooring & dadoing in toilet – 100% completed.
  • PVC Beading above skirting & Dadoo – 100% completed.
  • Steel Reinforcement for slabs & Beams – 100% completed.
  • M.S. Railing for stair case – 100% completed.
  • Plastering Internal – 100% completed.
  • External Plastering – 100% completed.
  • Water proofing plaster20mm thick for O.H.T – 100% completed.
  • Water proofing in terrace, retaining wall & toilets – 100% completed.
  • Painting O.B.D – 100% completed.
  • A.T.T – 100% completed.
  • Wooden Flooring – 90.40% completed.
  • C.P. Fitting in flats – 88% completed.
  • Lift Work – 30% completed.
  • External painting including hand railing – 30% completed.
  • False Ceiling in toilets & Kitchen – 60% completed.
  • Insulation of sanitary pipes – 98.21% completed.
  • Lobby Flooring – 50% completed.
  • Doors & Fittings - 93.50% completed.
  • Door Polishing - 64.77% completed.
  • Fenesta Doors & Windows – 87.21% completed.
Block A Wing III
  • Excavation in all kinds of soil for foundation – 100% completed.
  • Laying P.C.C - 100% completed
  • M25 Grade for Raft – Slab & Lift – Pit - 100% completed
  • M20 grade for Retaining Wall - 42% completed
  • M45 for column junctions Lower – Basement & Upper Basement - 75% completed
  • Steel – Reinforcement for foundation (Raft) - 100% completed
  • Steel – Reinforcement for Upper Basement floor - 100% completed
  • Shuttering for columns & G.F. Roofslab – 60% completed
STP
  • Earthwork Exacavation - 100% completed
  • P.C.C - 81% completed
  • Concreting – 34.27% completed.
  • Shuttering – 42% completed
  • Reinforcement – 51% completed.
BLOCK – A / WING – I&II
  • Over all Conduiting – 92% completed.
  • Switch Box Fixing – 98% completed.
  • Circuitry Wiring – 88.88% completed.
  • Point Wiring – 85.88% completed.
  • Switch plate Fixing - 13.33% completed.
  • Testing 4.65% completed.
  • Head over of flats – 2.32% completed.
Electrical Internal work Progress Wing – II
  • Over all Conduiting – 80.86% completed.
  • Switch Box Fixing – 95.83% completed.
  • Circuitry Wiring – 97.32% completed.
  • Point Wiring – 92.75% completed.
  • Switch plate Fixing - 98.55% completed.
  • Testing - 23.80% completed.
Electrical External work Progress Wing – I & II
  • Lift room & Shaft Electrical Works – 50% completed.
  • Electrical duct conduit works – 20% completed.
  • Cable Tray & Cable Works - 5% completed.



 
Project Summary
Project Type:
Residential Apartments

Location:
Sanjaynagar, Bangalore.

Distances:
7 kms from M.G. Road
11 kms from Airport

Unit Types:
2 & 3 Bedroom Apts.

Unit Cost:
Rs. 80 Lakhs onwards.
US$ 177,700 onwards.

Project Status:
Under Construction

Purva Privileges
A first of its kind Program in the Indian Real Estate Industry.

Refer and get rewarded
With Purva Privileges you can refer a friend or a relative to us and get rewarded.

» Learn More


Puravankara Projects Ltd : Leading real estate developers in India ; provides residential flats & commercial properties.

© Copyright 2006. ® All rights reserved.