- General Earth Work Excavation: Block A, B, C, D & PODIUM – Completed.
- Earth Work Excavation for Footings: Block A, B, C, D & PODIUM – Completed.
- Rock cutting: Block C & D – Completed.
- PCC 1:4:8 Leveling course for footings: Block A, B, C, D & Podium - Completed.
- Column Footings/ pedestal & raft beam concreting: Block A, B, C, D & Podium – Completed.
- Tie beams: Block A&C-100% Completed.
- Basement Floor column concreting – 100% Completed.
- Retaining wall: Block A,B,C&D-100% Completed.
- Basement Floor column concreting: Block A,B,C,D & Podium – Completed.
- PCC for flooring in basement: 100% Completed.
- Basement floor ceiling plastering: 100% Completed.
- Basement Storm water drain – Block A,B,C,D - 100% Completed, Podium – 100% Completed.
- Fire fighting works in basement Floor – 100% Completed.
GROUND FLOOR
- Slab Concreting: Block A, B, C, D & - Podium – Completed.
- Column Concreting: Block A, B, C & D - Completed.
- Block work: Block A, B, C & D - Completed.
- Ground floor ceiling plastering: Block A, B, C & D - Completed.
- Painting work: A,B,C & D – 100% Completed.
- Fire fighting works: Block A, B, C & D - Completed.
FIRST FLOOR
- Slab Concreting: Block A, B, C & D – Completed.
- Column Concreting: Block A, B, C & D - Completed.
- Block work: Block A,B,C, & D - Completed.
- Electrical wall conduiting & box fixing: Block A,B,C& D - Completed.
- Plumbing wall chasing & GI line fixing: Block A,B,C& D - Completed.
- Internal wall & ceiling plastering: Block A,B,C, & D - Completed.
- Flooring: Block A,B ,C&D - Completed.
- Dado in Toilets: Block A, B , C&D - Completed.
- Painting work: Block A, B ,C & D – Completed..
- Fire fighting works: Block A, B ,C & D Completed.
SECOND FLOOR
- Slab Concerting: Block A, B, C & D - Completed.
- Column Concerting: Block A, B, C & D - Completed.
- Block work: Block A, B, C& D - Completed.
- Electrical wall conduiting & box fixing: Block A, B, C& D - Completed.
- Plumbing wall conducting & GI line fixing: Block A, B, C& D - Completed.
- Internal wall & ceiling plastering: Block A, B, C& D - Completed.
- Flooring: Block A, B, C&D Completed.
- Dado in toilets: Block A, B, C& D - Completed.
- Painting work: Block A, B, C&D- Completed.
- Fire fighting work: Block A, B, C&D Completed.
THIRD FLOOR
- Slab Concerting: Block A, B, C & D - Completed.
- Column Concerting: Block A, B, C & D - Completed.
- Block work – Block A,B, C & D – Completed.
- Electrical wall conduiting & box fixing – Block A,B, C & D Completed.
- Plumbing wall casing & GI line fixing: Block A,B,C& D - Completed.
- Internal wall & ceiling plastering: Block A,B,C& D - Completed.
- Flooring: Block A,B, C& D - Completed.
- Dado in toilets: Block A,B,C & D - Completed. .
- Painting work: Block A,B,C & D - Completed. .
- Fire fighting works: Block A,B,C& D - Completed.
FOURTH FLOOR
- Slab Concerting: Block A, B, C & D – Completed.
- Column Concreting: Block A, B, C & D - Completed.
- Block work: Block A, B,C& D - Completed.
- Electrical wall conduiting & box fixing: Block A,B,C& D - Completed.
- Plumbing wall chasing & GI line fixing: Block A,B,C& D - Completed.
- Internal wall & ceiling plastering: Block A, B,C& D-Completed.
- Flooring: Block A, B, C&D Completed.
- Dado in toilets: Block A, B, C& D - Completed.
- Painting work: Block A, B,C&D- Completed.
- Fire fighting work: Block A, B,C&D- Completed.
FIFTH FLOOR
- Slab Concerting: Block A, B, C & D – Completed.
- Column Concreting: Block A, B, C & D – Completed.
- Block work: Block A,B,C& D-Completed.
- Electrical wall conduiting & box fixing: Block A,B,C& D - Completed.
- Plumbing wall conducting & GI line fixing: Block A,B,C& D - Completed.
- Internal wall & ceiling plastering: Block A,B,C& D - Completed.
- Flooring: Block A,B,C&D Completed.
- Dado in toilets: Block A,B,C& D - Completed.
- Painting work: Block A,B,C & D - Completed.
- Fire fighting work: Block A,B,C & D - Completed.
SIXTH FLOOR
- Slab Concreting: Block A, B, C & D – Completed.
- Column Concreting: Block A, B, C & D – Completed.
- Block work: Block A,B,C& D - Completed.
- Electrical wall conduiting & box fixing: Block A,B,C& D - Completed.
- Plumbing wall conducting & GI line fixing: Block A,B,C& D - Completed.
- Internal wall & ceiling plastering: Block A,B,C& D - Completed.
- Flooring: Block A,B,C&D Completed.
- Dado in toilets: Block A,B,C& D - Completed.
- Painting work: Block A,B,C & D - Completed.
- Fire fighting work: Block A,B,C & D - Completed.
SEVENTH FLOOR
- Slab Concreting: Block A, B, C & D – Completed.
- Column Concreting: Block A, B, C & D – Completed.
- Block work: Block A,B,C& D - Completed.
- Electrical wall conduiting & box fixing: Block A, B, C& D - Completed.
- Plumbing wall conducting & GI line fixing: Block A, B, C& D - Completed.
- Internal wall & ceiling plastering: Block A,B,C& D - Completed.
- Flooring: Block A,B,C&D Completed.
- Dado in toilets: Block A,B,C& D - Completed.
- Painting work: Block A,B,C & D - Completed.
- Fire fighting work: Block A,B,C & D - Completed.
EIGHTH FLOOR
- Slab Concreting: Block A & C – Completed.
- Column Concreting: A & C – Completed.
- Block work: Block A &C -Completed.
- Electrical wall conduiting & box fixing: Block A & C-Completed.
- Plumbing wall conducting & GI line fixing: Block A &C -Completed.
- Internal wall & ceiling plastering: Block A & C-Completed.
- Flooring: Block A&C Completed.
- Dado in toilets: Block A&C-Completed.
- Painting work: Block A&C -100% Completed.
- Fire fighting work: Block A,B,C & D - Completed.
TERRACE
- Slab Concreting: Block A, B, C & D – Completed.
- Floor Column Concreting: Block A, B, C & D – Completed.
- Parapet block work: Block A,B,C & D-100%Completed
- Waterproofing: Block A,B,C& D - Completed.
- Fire fighting works: Block A,B,C & D - Completed.
- Lift Machine Room Concreting: Block A, B, C & D – Completed.
- Staircase headroom Concreting: Block A, B, C & D – Completed.
- Over Head Tank Concreting: Block A, B, C & D – Completed.
- Podium Water Proofing Work – 100% Completed.
- Lift pit filling: Block A,B,C& D - Completed.
- P.O.P. works: Block A,B,C& D - Completed.
- Stair case flooring: Block A,B,C& D - Completed.
- Electrical Internal wiring: Block A,B,C&D – Completed.
- External plumbing works: A,B,C&D – Completed.
- External plastering: Block A, B,C&D- Completed.
- External painting: Block A,B,C & D – 98% Completed.
- STP works: 100% Completed.
- Swimming Pool excavation: Completed.
- Swimming pool civil works: Completed.
- Sump tank Excavation: Completed.
- Sump tank civil work: Completed.
- Sump tank excavation (External): Completed.
- External storm water drain: Completed.
- Landscaping Civil Works: Completed.
- Compound Wall (A B C D): Completed.
- Entrance gate works: Completed.
- Club House works: Completed
|
|
& nbsp; |
| Project Summary |
Project Type:
Residential Apartments
Location:
JP Nagar 6th Phase, Bangalore.
Distances:
12 kms from M.G. Road
Unit Types:
2 & 3 Bedroom Apts.
Project Status:
Under Construction
|
|
 |
| |
 |
Purva Privileges
A first of its kind Program in the Indian Real Estate Industry.
Refer and get rewarded
With Purva Privileges you can refer a friend or a relative to us and get rewarded.
» Learn More |
 |
|