Status report of Purva Highlands as on 30.04.08
Photographs as on 29.02.08

Phase I: Blocks - L, M, N, J, K, G & H
Phase II: Blocks- E, F, D, C, B & A
  • Excavation for Basement and Raft slab: Block L, M, N, J, K, G, H, E ,F,D,C ,B,A -100% Completed.
  • Trimming and laying of Quarry dust: Block L, M, N, J, K, G, H, E ,F,D,C ,B,A – 100% completed.
  • PCC 1:3:6 for Bed concrete: Block L, M, N, J, K, G, H,F,E,D,C,B,A -100% Completed.
  • Marking of Shear walls, Columns etc for Raft: Block L, M, N, J, K, G, H, F,E,D,C,B,A-100% Completed.
  • Steel Fabrication for Raft slab: Block L, M, N, J, K, G, H , F,E,D,C,B,A – 100% Completed.
  • Shuttering for Raft slab: Block L, M, N, J, K , G, H, F,E,D,C,B,A -100% Completed.
  • RMC for Raft slab: Block L, M, N, J, K ,G , H ,F,E,D ,C,B,A-100% Completed.
  • Marking of shear walls, Columns etc for Raft: Block L, M, N, J, K , G, H,F,E,D,C,B,A -100% Completed.
  • Steel Fabrication for shear walls & columns: Block L, M, N , J, K, G, H , F,E,D,C – 100% Completed.
  • Shuttering for shear walls, Columns: Block L, M , N – 100% Completed.
  • Concrete for shear walls & Columns: Block L, M & N – 100%.
  • Earth work back filling: Block L, M & N – 100% Completed.
  • Antitermite Treatment: Block L, M, N –100% Completed.
  • Flooring concrete – Block L ,M & N – 100% Completed.
GF – FF/LB - UB
  • Reinforcement, Shuttering & Concreting – walls columns (Above grade slab for LMN): Block L ,M ,N ,J,K,G,H – 100% Completed, Block F – 90% Completed, Block E – 75% Completed, Block D – 30% completed , Block C – 20% completed.
  • Shuttering & formwork for Roof Slab: Block L, M,N,J ,K, G,H – 100% Completed,Block F – 45% Completed, Block –D – 30% completed..
  • Reinf. For Roof Slab GF/LB1: Block L, M, N ,J ,G :- 100% Completed, Block K –70% completed, Block G – 100% completed; Block H – 65% completed, Block F–20% completed.
  • Concrete for roof slab GF/LB1 – Block L ,M,N,J,G – 100% Completed, Block – K - 50% completed, Block H – 60% completed.
  • Block Masonry Works : Block L, M,N – 100% completed.
  • Making & Fixing of Door Frames – Block L,M,N – 100% completed.
  • Internal Plastering – Block L,M,N – 100% Completed, Block J –95% completed, Block G-95% completed.
  • Service Road : 25% Completed
  • Compound Wall: 65% Completed.
FF – 2F/UB - GF
  • Reinforcement, Shuttering & Concreting – walls columns – Block L,M, N,J,G – 100% completed; Block H –30% completed.
  • Shuttering & formwork for Roof Slab - Block L,M,N,G,J– 100% completed.
  • Reinf. For slab & beams – Block L,M, N ,J,G– 100% completed
  • Concrete for roof slab FF/UB - Block L,M, N ,J,G– 100% completed .
  • Block Masonry Works – Block L, M & N – 100% completed.
  • Making & Fixing of Door Frames – Block L,M & N - 100% completed .
  • Internal Plastering – Block L ,M – 100% completed, Block N - 95% completed. Block J – 10% completed, Block G – 50% completed.
2F – 3F/GF – FF
  • Reinforcement, Shuttering & Concreting for walls & columns – Block L,M,N, J, G – 100% completed, Block H – 30%completed.
  • Shuttering & Concreting for slab – Block L,M,N,J,G – 100% completed.
  • Reinforcement for Slabs & beams – Block – L,M,N,J,G – 100% completed.
  • Concreting of slabs (GF/3F – Roof Level) - Block – L,M,N,J,G – 100% completed.
  • Block Masonry Works – Block L,M ,N– 100% completed.
  • Making & Fixing of Door Frames – Block L,M ,N – 100% completed.
  • Internal Plastering – Block L, M – 100% completed; Block N -95% completed; Block J –10% completed; Block G –50% completed.
3.F – 4.F/1F – 2F
  • Rein., Shuttering Concreting for walls & columns – Block L,M,N,J,G – 100% completed.
  • Formwork for Shear wall/Columns/ Slabs/ Beams – Block L – 100% completed; Block N -100% completed
  • Casting of Shear wall/ Columns/Slabs /Beams – Block L – 100% completed, Block N -100% completed.
  • Block Masonry Works – Block L – 95% Completed; N– 75% completed.
4F – 5F/2F – 3F
  • Reinforcement for Shear wall / Columns/ Slabs / Beams – Block L - 100% , Block N – 100% completed.
  • Formwork for Shear wall/Columns/ Slabs/ Beams – Block L– 100% completed, Block N – 100% completed
  • Casting of Shear wall / Columns/Slabs/Beams – Block L – 100% completed; Block N – 100% completed.
  • Block Masonry Works – Block L – 25% Completed
5F – 6F / 3F – 4F
  • Reinforcement for Shear wall / Columns/Slabs/Beams – Block L -100% completed; Block N – 40% completed.
  • Formwork for Shear wall / Columns/Slabs/Beams – Block L – 100% Completed; Block N – 50% completed.
  • Casting of Shear wall / Columns/Slabs/Beams - Block L 60% completed; Block N – 30% completed.
6F – 7F / 4F – 5F
  • Reinforcement for Shear wall / Columns/Slabs/Beams – Block L -100% completed.
  • Formwork for Shear wall / Columns/Slabs/Beams – Block L – 100% Completed.
  • Casting of Shear wall / Columns/Slabs/Beams - Block L 100% completed.
OTHER WORKS:
  • Service Road – 85% completed.
  • Compound Wall – 90% completed
  • Retaining Wall for Compound near LMN Wing: 96%
Progress Pictures as on 29th February, 2008.
     
     
     



 
Project Summary
Project Type:
Residential Apartments

Location:
Kanakapura Road, Bangalore.

Unit Types:
2 & 3 Bedroom Apts.

Unit Sizes:
1339 - 1841 sq.ft.

Unit Cost:
Rs. 41 Lakhs onwards.
US$ 91,000 onwards.

Project Status:
Under Construction.

Completion:
Phase 1 - September 2009
Purva Privileges
A first of its kind Program in the Indian Real Estate Industry.

Refer and get rewarded
With Purva Privileges you can refer a friend or a relative to us and get rewarded.

» Learn More


Puravankara Projects Ltd : Leading real estate developers in India ; provides residential flats & commercial properties.

© Copyright 2006. ® All rights reserved.