Mass Excavation: Block A, B, C, D, E, F, G, H, J, K, L, M & N, - Completed, Club house – Completed, Compound wall side A, B, C, D, F, G, H & P - 100% Completed.
Plain Cement Concrete: Block A, B, C, D, E, F, G, H, J, K, L, M & N- Completed, Club house – Completed, Compound wall side A, B, C, D, F, G, H & P – Completed.
Footing: Block A, B, C, D, E, F, G, H, J, K, L, M & N - Completed, Club house – Completed.
Pedestal: Block A, B, C, D, E, F, G, H, J, K, L, M, N, & Club house – Completed.
Tie Beams: Block G – 100% Completed.
Columns: Blocks A, B, C, D, E, F, G, H, J, K, L, M, N, & Club House – Completed.
Below Base Columns: Block G – 100% Completed.
Retaining Wall: Block A, B, C, D, E, F, G, H, J, K, L, M, N & Club House Completed.
Soiling: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Club House Completed.
Plain Cement Concrete: Block A, B, C, D, E, F, G, H, J, K, L, M & N Completed. Clubhouse Completed.
Size Stone Masonry: Block A, B, C, D, E, F, H, J, K, L M – Completed, Compound side A, B, C,D, F ,G, H & P, - Completed.
D.P.C for compound wall: A, B, C,D, F ,G, H & P, - Completed; Compound side A, B, C,D, F ,G, H & P, - Completed.
Block work: Compound side A, B, C,D, F,G,H & P – Completed.
Ground floor slab (PODIUM): Block A, B, C, D, E, F, G, H, J, K, L ,M,N– Completed. Club House – Completed.
Ground floor slab: Block A, B, C, D, E, F, G, H, J, K, L, M, & N Completed, Club House – Completed.
Ground floor Plastering: Block A, B, C, D, E, F, G, H, J, K, L, M, N – Completed, Club house-Completed.
Ground floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N & Club House – Completed.
First Floor:
First floor slab: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Club House- Completed.
First floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M & N– Completed, and Club House Completed.
Block Work: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Club House – Completed.
Internal Plastering: Block A, B, C, D, E, F, G, H, J, K, L, M, N – Completed, Club House – 100% Completed.
Flooring: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Club House-100% Completed.
Second Floor:
Second floor slab: Block A, B, C, D, E, F, G, H, J, K, L, M, & N – Completed, Club House- 100% Completed.
Second floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Club house – 100% Completed.
Block work: Block A, B, C, D, E, F, G, H, J, K, L, M, N and Club House – 100% Completed.
Plastering: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Club House-100% Completed.
Flooring: Block A, B, C, D, E, F, G, H, J, K , M, N & L Completed, Club House-100% Completed.
Third Floor:
Third Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Clubhouse – 100% Completed.
Third Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M & N, – Completed, Clubhouse – 100% Completed.
Block Work: Block A, B, C, D, E, F, G, H, J, K, L, M & N Completed. Club House – 100% Completed.
Plastering: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed, Club House – 100% Completed
Flooring: Block A, B, C, D, E, F, G, H, J, K, L, M &N Completed, Club house -100% Completed.
Fourth Floor:
Fourth Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, & N. – Completed.
Fourth Floor Columns: Block A, B, C, D, E, F, G H, J, K, L, M, & N – Completed.
Block Work: Block A, B, C, D, E, F, G, H, J, K, L M & N – Completed.
Plastering: Block A, B, C, D, E, F, G, H, J, K, L, M, N- Completed.
Flooring: Block A, B, C, D, E, F, G, H, J, K, L, M &N -Completed.
Fifth Floor:
Fifth floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed.
Fifth floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M & N– Completed,
Block Work: A, B, C, D, E, F, G, H, J, K, L, M,& N– Completed,
Plastering: Block A, B, C, D, E, F, G, H, J, K, L, M,&N Completed.
Flooring: Block A, D, E, F, G, H, J, K, L, M &N Completed.
Sixth Floor:
Sixth floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, & N – Completed.
Sixth floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M,& N– Completed.
Block Work: Block A, B, C, D, E, F, G, H, J, K, L, M & N– Completed
Plastering: Block A, B C, D, E, F, G, H, J, K, L, M, & N – Completed.
Flooring: Block A, B C, D, E, F, G, H, J, K, L, M&N, – Completed.
Seventh Floor:
Seventh floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed.
Seventh floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M & N – Completed.
Block Work: Block A, B, C, D, E, F, G, H, J, K, L, M &N – Completed,
Plastering: Block A, B, C, D, E, F, G, H, J, K, L, M &N Completed.
Flooring: Block A, B, C, D, E, F, G, H, J, K, L,M &N– Completed.
Eighth Floor
Eight floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N – Completed.
Eight floor Columns: A, B, C, D, E, F, G, H, J, K, L, M, N – Completed.
Block Work: Block A, B, D, E, F, G, H, J, K, L, M, N - Completed,
Plastering: Block A, B, C, D, E, F,G, H, J, K, L, M, N – Completed,
Flooring: Block A, B, C, D, E, F, H, J, K,L, M &N – Completed.
Terrace Floor Slab: Block A, B, C, D, E, F, G, H, J, K, L, M, N – Completed.
Terrace Floor Columns: Block A, B, C, D, E, F, G, H, J, K, L, M, N – Completed.
Terrace Floor Block Work: Block A, B, C, D, E, F, G, H, J, K, L, M, N– Completed
Slope Roof, LMR, and OHT – STR: Block A, B, C, D, E, F, G, H, J, K, L, M, N – Completed.
Road Work: 100% Completed.
Landscaping: 90% Completed.
Project Summary
Project Type:
Residential Apartments
Location:
Bannerghatta Main Road, Bangalore.
Distances:
13 kms from M.G. Road
13 kms from Airport
22 kms from Rly. Station
Unit Types:
2 & 3 Bedroom Apts.
Project Status:
Under construction
Completion:
November 2006 (Phase 1)
March 2007: Only Blocks PA, PB, PC (Phase 2)