Status report of Purva Parkridge as on 31.10.07
Photographs as on 26.10.2007» See Progress Photographs

Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B
  • Marking: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Excavation: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Anti - Termite Treatment: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Plain Cement Concrete: Villa 1C, 2C 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Footing: Villa1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Column unto Ground Floor Roof: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Size Stone masonry: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Plinth Beam: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Block Masonry up to Ground Floor lintel Level: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Ground Floor Lintel: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Block Masonry above Ground Floor Lintel: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Ground Floor Roof Slab Work: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 9B & 10B - Completed.
  • Columns unto M/F Roof: Villa 10B- Completed.
  • Size Stone Masonry -: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Plinth Beam - : Villa: 1C, 2C, 3C, 4C, 5C, 6C, 7B ,8B, 9B, 10B - Completed.
  • Block Masonry work up to First Floor Lintel Level: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • G/F Roof slab: Villa: 1C, 2C, 3C, 4C, 5C, 6C, 7B , 8B, 9B, 10B - Completed.
  • First Floor Lintel: Villa: 1C, 2C, 3C, 4C, 5C, 6C, 7B 8B, 9B, 10B - Completed.
  • Block masonry above First Floor Lintel: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • M/F Roof: Villa 10B- Completed.
  • Columns upto F/F Roof: Villa 10B- Completed.
  • First Roof Slab: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Internal Plastering: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Flooring: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B, 10B, -Completed,
  • External Plastering: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Fixing of Mangalore tiles for roof: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • Internal Painting: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
  • External Painting: Villa 1C, 2C, 3C, 4C, 5C, 6C, 7B, 8B, 9B & 10B - Completed.
Villa 11B, 12B, 13B, 14B, 15C & 16C Town Houses Th 17B, Th 18A, Th 19B & Th 20B
  • Marking: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B, Th 20B - Completed.
  • Excavation Work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B, 20B - Completed.
  • Anti - Termite Treatment work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B, 20B - Completed.
  • Plain Cement Concrete: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B, 20B - Completed.
  • Footing Work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B, 20B - Completed.
  • Column Work upto Ground Floor Roof: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B, 20B - Completed.
  • Size Stone Masonry Work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B, 20B - Completed.
  • Plinth Beam Work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B & - Th 20B - Completed.
  • Block Masonry work Up to Ground Floor lintel Level: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A, Th 19B & Th 20B - Completed.
  • Ground Floor Lintel Work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A Th 19B & Th 20B - Completed.
  • Block Masonry above Ground Floor Lintel: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A & Th 19B & 20B - Completed.
  • Ground Floor Roof Slab Work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town House Th B17, Th A18, Th B19 & Th B20 Completed.
  • Column upto Mezzanine Floor Roof Work: Town Houses Th B17, Th A18, Th B19 & Th 20B - Completed.
  • Block Masonry Work up to First Floor Lintel: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A Th 19B & 20B - Completed.
  • First Floor Lintel Work: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town Houses Th 17B, Th 18A & Th 19B & 20B Completed.
  • Block Masonry Work Above First Floor Lintel: Villa 11B, 12B, 13B, 14B, 15C & 16C - Completed, Town House Th B17, Th A18 Th B19 TH 20B Completed.
  • Mezzanine Floor Roof Work: Town Houses Th B17, Th A18, Th B19 & Th 20B - Completed.
  • Column up to First Floor Roof: Town Houses Th B17, Th A18, Th B19 & Th 20B- Completed.
  • First Floor Roof Slab: Villa 11B, 12B, 13B, 14,B, 15C & 16C - Completed, Town House Th B17, Th A18, Th B19 & Th 20B Completed.
  • Internal Plastering Work: Villa 11B, 12B, 13B, 14, B, 15C & 16C - Completed, Town House Th B17, Th A18, Th B19 & Th 20B Completed.
  • Flooring: Villa 11B, 12B, 13B, 14, B, 15C & 16C - Completed, Town House Th B17, Th A18, Th B19 & Th 20B Completed.
  • External Plastering : Villa 11B,12B, 13B,14B, 15C, 16C Th B17, A18 & B19, 20B,- Completed,
  • Fixing of Mangalore tiles for Roof: Villa 11B, 12B, 13B, 14, B, 15C & 16C - Completed, Town House Th B17, Th A18, Th B19 & Th 20B Completed.
  • Internal Painting: Villa 11B, 12B, 13B, 14,B, 15C & 16C - Completed, Town House Th B17, Th A18, Th B19 & Th 20B Completed.
  • External Painting: Villa 11B, 12B, 13B, 14,B, 15C & 16C - Completed, Town House Th B17, Th A18, Th B19 & Th 20B Completed.
Town Houses Th 21A, Th 22A, Th 23B,Th 24B, Th 25A, Th 26A, Th 27B, Th 28B, 29A & 30B
  • Marking: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, Th 27B, Th 28B, 29A & 30B - Completed.
  • Excavation: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, Th 27B, Th 28B, 29A & 30B - Completed.
  • Anti - Termite Treatment work: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, Th 27B, Th 28B, 29A & 30B - Completed.
  • Plain Cement Concrete: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, & Th 27B, Th 28B, 29A & 30B - Completed.
  • Footing Work: Th 21A, Th 22A, Th 23B - Completed, Th 24B, Th 25A, Th 26A, Th 27B, Th 28B, 29A & 30B - Completed.
  • Column Work up to Ground Floor Roof: The 21A, The 22A, The 23B, Th 24B, Th 25A, Th 26A, Th 27B, Th B 28, Th A 29 & Th B 30 - Completed.
  • Size Stone Masonry Work: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, Th 27B, Th B28, Th A29 & Th B30 - Completed.
  • Plinth Beam: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, Th 27B, Th B 28, Th A 29 & Th B 30 - Completed.
  • Block Masonry upto Ground Floor Lintel level: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, 26A, Th 27B, Th 28B, Th 29A & Th 30B - Completed.
  • Ground Floor Lintel : Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, 26A, 27B, Th 28B, Th 29A & Th 30B - Completed.
  • Block Masonry above Ground Floor Lintel: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, 26A, TH 27B, Th 28B, Th 29A & Th 30B - Completed.
  • Ground floor roof slab: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, & Th 27B, Th 28B, 29A & 30B - Completed.
  • Column upto Mezzanine Floor Roof: Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, & Th 27B, Th 28B, 29A & 30B - Completed.
  • Block Masonry upto First Floor Lintel Level : Th 21A, Th 22A, Th 23B, Th 24B, TH 25A, TH 26A, TH27A, Th B 28, Th A 29 & Th B 30 - Completed,
  • First Floor Lintel Level : Th 21A, Th 22A, Th 23B, Th 24B, Th 25A TH 26A Th 27B , Th B 28, Th A 29 & Th B 30 - Completed,
  • Block Masonry above First Floor Lintel Level : Th 21A, Th 22A, Th 23B, Th 24B, Th 25A Th 26A, Th 27B,Th B28, Th A 29 & Th B 30, - Completed.
  • Mezzanine Floor Roof Work : Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, & Th 27B, Th 28B, 29A & 30B - Completed.
  • Column upto First Floor Roof : Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, & Th 27B, Th 28B, 29A & 30B - Completed.
  • First Floor Roof Slab : Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th 26A, & Th 27B, Th 28B, 29A & 30B - Completed
  • Internal Plastering : Th 21A, Th 22Ath , Th 23B, Th 24B, Th 25A, Th 26A, & Th 27B 28B, 29A & 30B - Completed.
  • Flooring : Th 21A, Th 22A, Th 23B, Th 24B - Completed, Th 25, Th 26B, TH 27, TH 28, TH 29, TH 30,Completed,
  • External Plastering : Th 21A & Th 22A, Th 23B Th 24B, Th 25A,TH 26A, Th 27B, Th 28B, 29A & 30B Completed.
  • Fixing of Mangalore tiles for roof: Th 21A, Th 22A, Th 23B, Th 24B, 25A, 26A, 27B, Th 28B, 29A, & 30B -Completed,
  • Internal Painting : Th 21A Th 22A, Th 23B, Th 24B, Th 25 A, Th26A, Th 27B, Th28B, Th 29A, & 30B - Completed,
  • External Painting : Th 21A, Th 22A, Th 23B, Th 24B, Th 25A, Th26A, Th 27B, Th28B, Th 29A, & 30B Completed.
Villa 31C, 32C, 33B, 34B, 35C, 36C,Townhouse Th 37B, Th 38A, Th 39B & Th 40B
  • Marking: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Excavation: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Anti - Termite Treatment: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Plain Cement Concrete: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Footing: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & 40B- Completed.
  • Column upto Ground Floor roof : Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Size Stone masonry: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Plinth Beam: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Block Masonry upto Ground Floor lintel Level: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Ground Floor Lintel: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Block masonry Above Ground Floor Lintel Level : Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Ground Floor Roof Slab Work: Villa 31C, 32C, 33B, 34B, 35C & 36C, Th 37B, Th 38A,Th 39B & Th 40B - Completed.
  • Columns upto Mezzanine roof: Th 37B, Th 38A,Th 39B & Th 40B - Completed.
  • Block masonry upto First Floor Lintel Level: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • First Floor Lintel: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Block Masonry above First Floor Lintel: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Mezzanine roof: Th 37B, Th 38A, Th 39B & Th 40B - Completed.
  • Column upto First Floor Roof : Th 37B, Th 38A & Th 39B, Th 40B - Completed.
  • First Floor Roof Slab : Villa 31C, 32C, 33B, 34B, 35C & 36C, Th 37A, Th 38B,Th 39B & Th 40B - Completed.
  • Internal plastering : Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37B, Th 38A, Th 39B, Th 40B Completed.
  • Flooring: Villa 31C, 32C,Th 33B, 34B, 35C, 36C, 37B, 38A, Th 39B, Th 40B - Completed,
  • External Plastering: Villa 31C, 32C, 33B, 34B, 35C & 36C, Th 37B, Th 38A,Th 39B & Th 40B - Completed.
  • Fixing of M-lore tiles for roof : Villa 31C, 32C, 33B, 34B, 35C & 36C, Th 37A, Th 38B - Completed, Th 39B & Th 40B - Completed.
  • Internal Painting: Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37A, Th 38B,Th 39B Th 40B - Completed.
  • External Painting : Villa 31C, 32C, 33B, 34B, 35C, 36C, Th 37A, Th 38B,Th 39B & Th 40B - Completed.
Townhouse Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, 48B, 49A & 50B
  • Marking: Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47 B, Th 48B, Th 49A & 50B- Completed.
  • Excavation: Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & Th 50B - Completed.
  • Anti Termite: Th 41A, Th 42A, Th43B, Th 44B, Th 45 A, Th46A, Th47 B, Th 48B, Th 49A & Th 50B - Completed.
  • Plain Cement Concrete: Th 41A, Th 42A, Th43B, Th44B, Th45 A, Th46A & Th 47B Th48B, Th49A & Th 50B -Completed.
  • Footings: Th 41A, Th 42A, Th 43B, Th 44B, Th 45A, Th46A, Th 47 B, Th 48B, Th 49B & Th 50B- Completed.
  • Columns upto ground floor roof: Th 41A, Th 42A, Th 43B, Th 44B, Th 45 A, Th 46A, & Th 47 B - Completed, Th 48B, Th 49B & Th 50B - Completed.
  • Size Stone Masonry : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & 50B- Completed.
  • Plinth Beam : Th 41A, Th 42A, 43B, 44B, Th 45 A, 46A, 47B, Th 48B, Th 49A & Th 50B - Completed.
  • Block Masonry upto Ground Floor Lintel level: Th 41A, Th 42A, Th 43B, Th 44B, Th 45 A, 46A, 47 B, Th 48B, Th 49B & Th 50B - Completed.
  • Ground Floor Lintel : Th 41A, Th 42A, 43B, 44B, Th 45 A, Th 46A, Th 47 B, Th 48B, Th 49A & Th 50B - Completed.
  • Block Masonry above Ground Floor Lintel: Th 41A, Th 42A, Th 43B, Th 44B, Th 45 A, 46A, 47B, Th 48B, Th 49A & Th 50B - Completed.
  • Ground Floor Roof Slab: Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47 B, Th 48B, Th 49A & 50B- Completed.
  • Column Upto Mezzanine floor roof: Th 41A, Th 42A, 43B, 44B, 45A, 46A, 47B, Th 48B, Th 49A & Th 50B - Completed.
  • Block Masonry upto First Floor Lintel Level: Th 41A, Th 42A, Th 43B, Th 44B, 45 A, Th 46A, 47B, Th 48B, Th 49A & Th 50B - Completed.
  • First Floor Lintel : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & Th 50B - Completed.
  • Block Masonry Above First Floor Lintel : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & Th 50B - Completed.
  • Mezzanine Floor Roof : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & 50B- Completed.
  • Columns upto First Floor Roof : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & 50B- Completed.
  • First Floor Roof Slab : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & 50B- Completed.
  • Internal Plastering : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47 B, Th 48B, Th 49A & 50B- Completed.
  • Flooring : Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & 50B- Completed.
  • External Plastering: Th 41A, Th 42A, Th 43B, Th 44B Th 45A, Th 46A, Th 47B,48B, Th 49A, Th 50B - Completed.
  • Fixing of Mangalore tiles for roof: Th 41A, Th 42A, 43B, 44B, 45 A, 46A, 47B, Th 48B, Th 49A & Th 50B Completed.
  • Internal Painting: Th 41A, Th 42A, Th 43B, Th 44B, 45 A, 46A, 47B, 48B Th 49A & Th 50B Completed.
  • External Painting: Th41A, Th42A, Th43B, Th44B, Th45A, Th46A, Th47B, Th48B, Th49A & Th 50B Completed.
«  Page 1 |  Page 3  »

 
Project Summary
Project Type:
Luxury Villas
Townhouses

Location:
Off Ring Road, Marthahalli, Bangalore.

Distance:
13 kms from M.G. Road
6 kms from Airport
24 kms from Rly. Station

Project Status:
Under construction

Completion:
March 2006

Purva Privileges
A first of its kind Program in the Indian Real Estate Industry.

Refer and get rewarded
With Purva Privileges you can refer a friend or a relative to us and get rewarded.

» Learn More


Puravankara Projects Ltd : Leading real estate developers in India ; provides residential flats & commercial properties.

© Copyright 2006. ® All rights reserved.