Staircase (Twelveth floor to thirteenth floor ): 100.00% Completed.
Staircase (Thirteenth floor to terrace floor ): 100.00% Completed
Slab Concreting floor wise
Upper basement Floor 79.14 % Completed.
Lower basement floor 3.79% Completed.
Ground floor Slab: 97.06% Completed.
First floor: 100% Completed.
Second floor: 100% Completed.
Third floor: 100% Completed.
Fourth Floor: 100% Completed.
Fifth floor : 100% Completed.
Sixth floor : 100.00% Completed.
Seventh floor 100.00% Completed.
Eighth floor 100.00% Completed.
Ninth floor 100.00% completed.
Tenth floor 100.00% Completed.
Eleventh floor 100.00% Completed.
Twelveth floor 100.00% completed.
Thirteenth floor 97.71% completed.
Terrace floor 95.16% completed.
STP 62.77% completed.
Sump Tank 100% completed.
Ramps work:
Lower basement floor to upper basement floor ramp work 100% completed.
Upper basement floor to Ground floor podium 100% completed.
Flooring:
Marble:
First Floor: 100.00% completed.
Second Floor: 100.00% completed.
Third Floor: 100.00% Completed.
Fourth Floor: 83.33% Completed.
Fifth Floor: 100.00% Completed.
Sixth Floor: 100.00% Completed.
Seventh Floor: 83.33% Completed.
Eighth Floor 66.67 % completed.
Ninth Floor 50.00% completed.
Tenth Floor 33.33% completed.
Vitrified Tiles:
First Floor: 100.00% Completed.
Second Floor: 100.00% Completed
Third Floor: 83.33% Completed.
Fourth Floor: 66.67% Completed
Fifth Floor : 66.67% completed
Sixth Floor: 66.67% completed.
Seventh Floor : 66.67% completed.
Eighth Floor : 66.67% completed.
Cotto tiles for toilets:
First Floor: 100.00% Completed.
Second Floor:100.00% Completed
Third Floor: 83.33% Completed
Fourth Floor : 66.67% Completed.
Fifith Floor: 66.67% Completed.
Sixth Floor: 66.67% Completed.
Seventh Floor 66.67% completed
Eighth Floor : 66.67% completed.
Block work:
1st floor 100.00% completed.
2nd floor 100.00% completed
3rd floor 100.00 % completed
4th floor 100.00 % completed
5th floor 100.00 % completed
6th floor 100.00 % completed
7th floor 100.00 % completed.
8th floor 100.00% completed.
9th floor 100.00% completed.
10th floor 100.00% completed.
11th floor 83.33% completed
12th floor 83.33% completed
13th floor 50.00% completed.
For lift shafts block work:
From GF to 9th floor 94.12% completed.
Wall Plastering :
1st floor 100.00% completed
2nd floor - 100.00 completed
3rd floor 100.00% completed
4th floor 83.33% completed.
5th floor 100.00% completed.
6th floor 100.00% completed.
7th floor 100.00% completed.
8th floor 100.00% completed.
9th floor 50.00% completed
10th floor 66.67% completed.
11th floor 50.00% completed.
Ceiling plaster :
1st floor 100.00% completed.
2nd floor -100.00% completed
3rd floor 100.00% completed
4th floor -91.67% completed
5th floor 100.00% completed
6th floor 100.00% completed.
7th floor 100.00% completed.
8th floor 100.00% completed.
9th floor 100.00 % completed.
10th floor 83.33% completed.
11th floor 66.67% completed.
Aluminum sub frame work:
1st floor 100.00% completed.
2nd floor 100.00% completed
3rd floor 100.00% completed
4th floor 83.33 % completed
5th floor 83.33 % completed
6th floor 83.33 % completed
7th floor 83.33 % completed
8th floor 83.33% completed.
9th floor 66.67% completed.
10th floor 66.67% completed.
Plumbing work:
1st floor 100.00% completed.
2nd floor 100.00% completed.
3rd floor 100.00% completed.
4th floor 83.33% completed.
5th floor 100.00% completed.
6th floor 100.00% completed.
7th floor 66.67% completed.
8th floor 66.67 % completed.
9th floor 50.00% completed.
10th floor- 33.33% completed.
Electrical work:
First floor 100.00% completed.
Second floor 100.00% completed.
Third floor 100.00% completed.
Fourth floor 83.33% completed.
Fifth floor 100.00% completed.
Sixth floor 100.00% completed.
Seventh floor 100.00% completed.
Eighth floor 100.00% completed.
Ninth Floor 83.33 % completed
Tenth Floor 83.33% completed
11th floor 50.00% completed.
External wall plastering:
From GF to terrace (Including duct) : 36.95% completed.
Staircase area + corridor 75.34% completed.
Quarry dust filling (App.):57.14% Completed.
Crane Footing: 100.00%.
Providing G.I barricade all around the site, for a height of 6mt: 52.03% Completed.
Photographs as on 26.05.2008
Project Summary
Project Type:
Residential Apartments
Location:
HSR Layout, Bangalore.
Distances:
15 kms from M.G. Road
14 kms from Airport
24 kms from Rly. Station
Unit Types:
2 & 3 Bedroom Apts.
Unit Cost:
Rs. 85.91 Lakhs onwards.
US$ 190,900 onwards.
Project Status:
Under Construction
Completion:
Septemebr 2008