Status report of Purva Vantage as on 31.05.08
Photographs as on 26.05.08» See Progress Photographs
Below Basement Level:
  • Rock excavation for footings & Foundation: 99.99% Completed.
  • Internal Footings: 100.00% Completed.
  • External Footings: 88.73% Completed.
  • Internal Pedestals Below (85.55 Level): 100.00% Completed.
  • Internal Columns Below (85.55 Level): 100.00% Completed.
  • Internal Columns Above (85.55 Level): 100.00% Completed.
  • Internal Tie beams 1st Level: 100% Completed.
  • Internal Tie beams 2nd level: 100.00% Completed.
  • Internal Tie beams 3rd level: 100.00% Completed.
  • External Column up to (84.95Lvl): 81.69% Completed.
  • External Column up to (87.8 Level): 81.69% Completed.
  • External Tie beam connecting Retaining wall (84.95Lvl): 47.22% Completed.
  • External Tie beam connecting Retaining wall (87.8Lvl): 36.84% Completed.
  • Retaining Wall up to (88.55 Level): 51.96% Completed.
  • Retaining Wall up to (88.55 Level): 21.98% Completed.
  • Collection well up to 88.55Lvl: 73.71% Completed.
  • Lift pit up to 13th floor: 100.00% Completed.
Above Basement Level:
  • Internal Columns above (85.55 Level):100.00% Completed.
  • External Column above (87.8 Level):36.62% Completed.
Above Upper Basement Level:
  • Columns (Internal): 100% Completed.
  • Columns (External): 77.46% Completed.
Staircase:
  • Staircase – (Lower basement to Ground Floor): 100.00% Completed.
  • Staircase – (Ground Floor to First Floor): 100.00% Completed.
  • Staircase – (Ground floor to Second floor): 100.00% Completed.
  • Staircase – (First to Second floor): 100.00% Completed.
  • Staircase – (Second to Third floor): 100.00% Completed.
  • Staircase – (Third floor to Fourth floor): 100.00% Completed.
  • Staircase – (Fourth to Fifth floor): 100.00% Completed.
  • Staircase – (Fifth to Sixth floor): 100.00% Completed.
  • Staircase – (Sixth to Seventh floor): 100.00% Completed.
  • Staircase – (Seventh to Eighth floor): 100.00% Completed.
  • Staircase – (Eighth to Ninth floor): 100.00% Completed.
  • Staircase – (Ninth to Tenth floor): 100.00% Completed.
  • Staircase – (Tenth to Eleventh floor): 100.00% Completed.
  • Staircase – ( Eleventh floor to Twelveth floor ): 100.00% Completed.
  • Staircase – (Twelveth floor to thirteenth floor ): 100.00% Completed.
  • Staircase – (Thirteenth floor to terrace floor ): 100.00% Completed
Slab Concreting floor wise
  • Upper basement Floor – 79.14 % Completed.
  • Lower basement floor – 3.79% Completed.
  • Ground floor Slab: 97.06% Completed.
  • First floor: 100% Completed.
  • Second floor: 100% Completed.
  • Third floor: 100% Completed.
  • Fourth Floor: 100% Completed.
  • Fifth floor : 100% Completed.
  • Sixth floor : 100.00% Completed.
  • Seventh floor – 100.00% Completed.
  • Eighth floor – 100.00% Completed.
  • Ninth floor – 100.00% completed.
  • Tenth floor – 100.00% Completed.
  • Eleventh floor – 100.00% Completed.
  • Twelveth floor – 100.00% completed.
  • Thirteenth floor – 97.71% completed.
  • Terrace floor – 95.16% completed.
  • STP – 62.77% completed.
  • Sump Tank – 100% completed.
  • Ramp’s work:
  • Lower basement floor to upper basement floor ramp work – 100% completed.
  • Upper basement floor to Ground floor podium – 100% completed.
Flooring:
  • Marble:
  • First Floor: 100.00% completed.
  • Second Floor: 100.00% completed.
  • Third Floor: 100.00% Completed.
  • Fourth Floor: 83.33% Completed.
  • Fifth Floor: 100.00% Completed.
  • Sixth Floor: 100.00% Completed.
  • Seventh Floor: 83.33% Completed.
  • Eighth Floor – 66.67 % completed.
  • Ninth Floor – 50.00% completed.
  • Tenth Floor – 33.33% completed.
Vitrified Tiles:
  • First Floor: 100.00% Completed.
  • Second Floor: 100.00% Completed
  • Third Floor: 83.33% Completed.
  • Fourth Floor: 66.67% Completed
  • Fifth Floor : 66.67% completed
  • Sixth Floor: 66.67% completed.
  • Seventh Floor : 66.67% completed.
  • Eighth Floor : 66.67% completed.
Cotto tiles for toilets:
  • First Floor: 100.00% Completed.
  • Second Floor:100.00% Completed
  • Third Floor: 83.33% Completed
  • Fourth Floor : 66.67% Completed.
  • Fifith Floor: 66.67% Completed.
  • Sixth Floor: 66.67% Completed.
  • Seventh Floor – 66.67% completed
  • Eighth Floor : 66.67% completed.
Block work:
  • 1st floor – 100.00% completed.
  • 2nd floor – 100.00% completed
  • 3rd floor – 100.00 % completed
  • 4th floor – 100.00 % completed
  • 5th floor – 100.00 % completed
  • 6th floor – 100.00 % completed
  • 7th floor – 100.00 % completed.
  • 8th floor – 100.00% completed.
  • 9th floor – 100.00% completed.
  • 10th floor – 100.00% completed.
  • 11th floor – 83.33% completed
  • 12th floor – 83.33% completed
  • 13th floor – 50.00% completed.
For lift shaft’s block work:
From GF to 9th floor – 94.12% completed.

Wall Plastering :
  • 1st floor – 100.00% completed
  • 2nd floor - 100.00 completed
  • 3rd floor – 100.00% completed
  • 4th floor – 83.33% completed.
  • 5th floor – 100.00% completed.
  • 6th floor – 100.00% completed.
  • 7th floor – 100.00% completed.
  • 8th floor – 100.00% completed.
  • 9th floor – 50.00% completed
  • 10th floor – 66.67% completed.
  • 11th floor – 50.00% completed.
Ceiling plaster :
  • 1st floor – 100.00% completed.
  • 2nd floor -100.00% completed
  • 3rd floor – 100.00% completed
  • 4th floor -91.67% completed
  • 5th floor – 100.00% completed
  • 6th floor – 100.00% completed.
  • 7th floor – 100.00% completed.
  • 8th floor – 100.00% completed.
  • 9th floor – 100.00 % completed.
  • 10th floor – 83.33% completed.
  • 11th floor – 66.67% completed.
Aluminum sub frame work:
  • 1st floor – 100.00% completed.
  • 2nd floor – 100.00% completed
  • 3rd floor – 100.00% completed
  • 4th floor – 83.33 % completed
  • 5th floor – 83.33 % completed
  • 6th floor – 83.33 % completed
  • 7th floor – 83.33 % completed
  • 8th floor –83.33% completed.
  • 9th floor – 66.67% completed.
  • 10th floor – 66.67% completed.
Plumbing work:
  • 1st floor – 100.00% completed.
  • 2nd floor – 100.00% completed.
  • 3rd floor – 100.00% completed.
  • 4th floor – 83.33% completed.
  • 5th floor – 100.00% completed.
  • 6th floor – 100.00% completed.
  • 7th floor – 66.67% completed.
  • 8th floor – 66.67 % completed.
  • 9th floor – 50.00% completed.
  • 10th floor- 33.33% completed.
Electrical work:
  • First floor – 100.00% completed.
  • Second floor – 100.00% completed.
  • Third floor – 100.00% completed.
  • Fourth floor – 83.33% completed.
  • Fifth floor – 100.00% completed.
  • Sixth floor – 100.00% completed.
  • Seventh floor – 100.00% completed.
  • Eighth floor – 100.00% completed.
  • Ninth Floor – 83.33 % completed
  • Tenth Floor – 83.33% completed
  • 11th floor – 50.00% completed.
External wall plastering:
  • From GF to terrace (Including duct) : 36.95% completed.
  • Staircase area + corridor – 75.34% completed.
Quarry dust filling (App.):57.14% Completed.
Crane Footing: 100.00%.
Providing G.I barricade all around the site, for a height of 6mt: 52.03% Completed.




Photographs as on 26.05.2008

     



 
Project Summary
Project Type:
Residential Apartments

Location:
HSR Layout, Bangalore.

Distances:
15 kms from M.G. Road
14 kms from Airport
24 kms from Rly. Station

Unit Types:
2 & 3 Bedroom Apts.

Unit Cost:
Rs. 85.91 Lakhs onwards.
US$ 190,900 onwards.

Project Status:
Under Construction

Completion:
Septemebr 2008
Purva Privileges
A first of its kind Program in the Indian Real Estate Industry.

Refer and get rewarded
With Purva Privileges you can refer a friend or a relative to us and get rewarded.

» Learn More


Puravankara Projects Ltd : Leading real estate developers in India ; provides residential flats & commercial properties.

© Copyright 2006. ® All rights reserved.